August 30, 2019
Boguchansky Aluminium Smelter Refractory Storage Facility
Currently, within the framework of the investment project "BEMO Project (Construction of Aluminum Smelter + Feasibility Study)" of BoAZ CJSC under the contract package Construction and installation work of the refractory warehouse the following work was accomplished:
• installation of ABA floors;
• sliding gates installed (3 pcs.);
• the installation of the entrance unit (2 pcs.)
• exterior finish of basement panels.
Work is underway on the installation of drywall walls and partitions.